Helping You Navigate The Complexities Of Your Case

Does your subcontractor agreement protect you? What you should check now.

by | Oct 5, 2026 | Business Law, Construction Law

A commercial general contractor in Westfield with forty employees runs every project on the same two-page subcontractor agreement it downloaded in 2014 and edited once. The form has caused no trouble in a decade, which is the usual reason nobody revisits it. Then an electrician’s apprentice falls from a ladder on a Noblesville job, the subcontractor’s carrier denies the claim, and the general contractor’s policy absorbs the loss. Reading the subcontract closely for the first time in years, the owner finds that the indemnity clause and the insurance requirements do not correspond to each other, and that neither one says what he assumed.

Subcontract forms tend to fail all at once rather than gradually, because a single incident tests several provisions simultaneously. Five sets of terms carry most of the risk in an Indiana construction subcontract, and each of them can be corrected in an afternoon with counsel. The discussion below identifies what Indiana law does with each set and what a contractor should look for in the form currently in use.

Indemnity and insurance have to be read together.

An indemnity clause determines who funds the defense and the judgment when someone is injured or property is damaged. Indiana limits how far that risk can be shifted downward. A provision in a construction or design contract other than a highway contract is void as against public policy to the extent it indemnifies a party against liability for death or bodily injury, property damage, or design defects arising from that party’s sole negligence or willful misconduct.

The statute was amended in 2019, and the amendment favors general contractors. The current version removed earlier references to the promisee’s agents, servants, and independent contractors, and clarified that sole negligence does not include vicarious liability, imputed negligence, or assumption of a nondelegable duty. Broad indemnity language remains enforceable up to that boundary, and a clause drafted for a state with a stricter statute may surrender protection Indiana would have permitted.

Broadening the clause without checking coverage creates a different problem. Commercial general liability policies fund contractual indemnity only within the definition of an insured contract, so an obligation drafted beyond that definition may be enforceable against the subcontractor and uncollectible in practice. Match the indemnity language to what the subcontractor’s coverage can actually reach, and involve your broker in the review rather than treating it as a purely legal question.

The insurance requirements should support the indemnity provision rather than sit beside it. Specify commercial general liability limits appropriate to the trade, additional insured status covering ongoing and completed operations, primary and noncontributory language, and a waiver of subrogation. Then require the endorsement rather than the certificate, because a certificate is a broker’s summary and the endorsement is the document granting coverage.

Is a pay-if-paid clause enforceable in Indiana?

A clause that clearly makes the general contractor’s receipt of payment a condition precedent to the subcontractor’s right to payment has been enforced under Indiana law. Language addressing only the timing of payment, such as payment within seven days of receipt from the owner, operates as a pay-when-paid provision and leaves the payment obligation intact. The difference between the two turns on the words the drafter chose.

The leading authority applying Indiana law came from the federal court of appeals rather than an Indiana appellate court, which is worth remembering before relying on it. The subcontract there stated that the owner’s acceptance of the work and payment to the contractor were conditions precedent to the subcontractor’s right to payment. When funding failed upstream, the court enforced the clause and held that the surety on the payment bond was no more liable than its principal.

A contingent payment clause does not reach every remedy. Indiana’s lien statute provides that an obligor’s receipt of payment from a third person may not be a condition precedent to, a limit on, or a defense to the right to record or foreclose a mechanic’s lien, subject to statutory exceptions for single and double family dwellings and certain utility property. A general contractor who shifts credit risk successfully under the subcontract may still face a lien against the customer’s building. That outcome is worth explaining to the customer before it happens.

An out-of-state form may or may not hold up here.

National subcontractors, suppliers, and equipment lessors distribute forms drafted for other jurisdictions, and those forms ordinarily select another state’s law and another state’s forum. An Indiana statute makes a provision in a contract for the improvement of real estate in Indiana void if it subjects the contract to the laws of another state or requires litigation, arbitration, or other dispute resolution to occur in another state. Our Court of Appeals has confirmed that the statute reaches contracts for the improvement of real estate generally rather than only disputes over mechanic’s liens, applying it to void a clause that would have sent a dispute over a Noblesville self-storage project to a Florida court. The Indiana Supreme Court has separately applied the statute to void an out-of-state choice of law provision.

The statute does less than its language suggests once arbitration is involved. Where the contract involves interstate commerce and the clause calls for arbitration, our Court of Appeals has held that the Federal Arbitration Act preempts the Indiana statute, reasoning that the statute singles out dispute resolution provisions in one category of contract instead of applying a defense available to contracts generally. A 2023 decision reaffirmed that analysis and left an arbitration proceeding in Wisconsin undisturbed. Construction contracts crossing state lines routinely involve interstate commerce.

The distinction has practical consequences. A clause requiring a lawsuit in another state stands on different footing from one requiring arbitration in another state, and a contractor who assumes the Indiana statute defeats both may find himself arbitrating in Dallas after declining to participate. The analysis turns on the particular contract and the nature of the transaction, so the provision is worth reviewing before the answer becomes expensive.

Flow-down and notice provisions decide who absorbs a change.

A flow-down provision binds the subcontractor to the terms of the prime contract between the owner and the general contractor. The provision is standard and defensible, and subcontractors sign it routinely without reading the document they have agreed to follow. The consequences surface later, ordinarily attached to a deadline.

One Indiana decision illustrates the exposure. A steel fabricator on a university project received revised drawings that substantially increased its scope of work. The prime contract required claims for additional payment to be initiated by written notice within twenty-one days, and the flow-down provision applied that requirement to the subcontractor. Written notice followed roughly eleven months later, and the claim failed as untimely notwithstanding the merits of the underlying work.

Subcontractors should request the prime contract before signing, or at minimum the general conditions and any claim provisions in it, and should calendar every notice deadline on the day the subcontract is executed. Where a general contractor declines to furnish the full document, ask specifically for the claims and notice articles. General contractors should confirm that their flow-down language actually incorporates the provisions they are relying on, because a general reference to the prime contract may not carry a specific claim deadline with it. Our post on handling delays in a central Indiana construction project addresses the same problem from the schedule side.

Payment terms, lien waivers, and licensing.

Retainage percentage, release conditions, and the documentation required with each payment application belong in the subcontract rather than in industry custom. Lien waiver practice deserves particular attention, because Indiana voids a provision requiring a person who furnishes labor, materials, or machinery to waive a lien or payment bond claim before being paid, subject to statutory exceptions for single and double family dwellings and certain utility property.

The distinction between conditional and unconditional waivers is where subcontractors most often lose money. A conditional waiver takes effect only upon actual receipt of the payment identified in it. An unconditional waiver releases the claim on its face, whether or not the check clears. Subcontractors should sign conditional waivers through payment and reserve unconditional waivers for funds already received. General contractors managing payment down the chain should consider joint check agreements with lower-tier subcontractors and suppliers, which reduce the risk that money paid once has to be paid twice.

Attorney fee provisions belong in the same conversation. Indiana follows the general rule that each side bears its counsel fees unless a contract or statute provides otherwise, so a fee-shifting clause determines whether a mid-size claim is worth pursuing. Mechanic’s lien claims carry a separate statutory fee rule that entitles a lienholder recovering a judgment to reasonable fees, subject to a limit protecting an owner who has already paid the contract consideration for the labor or materials at issue.

Licensing and permitting round out the review. Indiana does not issue a statewide general contractor license, plumbing is licensed at the state level, and other trades are regulated locally under requirements that differ from one municipality to the next. Confirm what Indianapolis, Fishers, Carmel, Noblesville, or Westfield requires for the particular scope before a subcontractor mobilizes, and place the obligation to hold current credentials and pull permits on the subcontractor in writing.

When to involve counsel.

A subcontract review costs a fraction of a single adverse claim, and it is most useful before any dispute exists, while terms can still be negotiated. Reviewing a form once and using it across a year of projects spreads the cost across every job. Several situations justify a call:

  • Your form predates 2019 and has not been checked against Indiana’s current anti-indemnity statute.
  • A subcontractor or supplier presents a form selecting another state’s law, courts, or arbitration forum.
  • You are asked to sign a flow-down provision without receiving the prime contract.
  • A certificate of insurance arrives without the endorsement, or the coverage does not match the subcontract requirements.
  • Payment has stalled upstream and you need to know whether your contingent payment clause holds.
  • A subcontractor abandons the work, or you are considering terminating one for default.

That last situation develops quickly and rarely resolves well without advice. A defective termination letter converts a defensible position into a breach claim, and the letter ordinarily goes out before anyone calls a lawyer. Our overview of what a construction dispute involves once it reaches litigation describes the process from that point, and the piece on common mistakes small contractors make addresses the practices that create these problems in the first place.

Frequently asked questions about subcontractor agreements in Indiana.

What should a subcontractor agreement include?

A defined scope with drawings and specifications attached, the price and payment terms, the schedule and any milestone dates, insurance requirements including additional insured status, an indemnity clause drafted to Indiana’s limits, and a change order procedure with notice deadlines. Add termination provisions covering default and convenience, safety and site rules, warranty terms, and an attorney fee clause. Keep dispute resolution in Indiana where the law permits.

Is a pay-if-paid clause enforceable in Indiana?

A clause that clearly makes payment from the owner a condition precedent to the subcontractor’s right to payment has been enforced under Indiana law. Language addressing only timing operates as a pay-when-paid provision and leaves the payment obligation in place. The wording controls the outcome, and neither version defeats mechanic’s lien rights, subject to the statutory exceptions.

Can I make my subcontractor indemnify me in Indiana?

Broadly, yes, subject to one statutory limit. Indiana voids a provision in a construction or design contract that indemnifies you against liability arising from your sole negligence or willful misconduct. The 2019 amendment clarified that sole negligence excludes vicarious liability, imputed negligence, and assumption of a nondelegable duty. Indemnity for shared fault remains available when the clause is drafted with that boundary in view and coordinated with available insurance.

Do subcontractors have to be licensed in Indiana?

It depends on the trade and the jurisdiction. Indiana has no statewide general contractor license, plumbing is licensed at the state level, and most other trades are regulated by the municipality or county where the work is performed. Requirements in Indianapolis differ from those in Fishers or Noblesville, so verify each jurisdiction and request proof before mobilization on every project.

What is an additional insured endorsement and do I need one?

An additional insured endorsement is the policy document extending the subcontractor’s coverage to you for liability arising out of the subcontractor’s work. A certificate of insurance is a broker’s summary and grants no coverage. Request the endorsement, confirm it reaches completed operations rather than ongoing operations alone, and note the form number, because different forms produce different results when a claim is tendered.

Can a subcontractor file a mechanic’s lien against my customer’s property?

Yes. A subcontractor who furnishes labor or materials improving the property can record a lien without any contract with the owner. That exposure is why lien waivers, joint check arrangements, and proof of payment down the chain matter to a general contractor. Deadlines run ninety days after last furnishing on most projects and sixty days on single and double family dwellings.

What is the difference between a conditional and unconditional lien waiver?

A conditional waiver becomes effective only when the payment identified in it is actually received. An unconditional waiver releases the claim on its face regardless of whether the payment clears. Subcontractors should use conditional waivers when exchanging paperwork for a check and reserve unconditional waivers for funds already received. Indiana also voids provisions requiring a waiver before payment, subject to statutory exceptions.

What happens if a subcontractor walks off the job?

Begin with the subcontract, because the notice and cure provisions in it govern what you may do and how quickly. Document the abandonment, the state of the work, and the cost to complete with a replacement. Follow the termination procedure closely, since a defective termination converts your claim into the subcontractor’s claim and places the excess completion cost out of reach.

Is a handshake deal with a subcontractor enforceable in Indiana?

An oral agreement between commercial parties can be enforceable, and proving its terms is the difficulty. Claims on contracts not in writing also carry a shorter limitation period. Without a written scope, price, and schedule, a dispute becomes a credibility contest between two people who each trust their recollection, so put it in writing even if the writing is a one-page purchase order.

Have your subcontract reviewed before it is tested.

A subcontractor agreement is among the least expensive risk management a construction business buys, and many of the forms circulating in central Indiana have not been examined closely in years. Fugate Gangstad Lowe LLC drafts and reviews construction contracts and subcontracts for general contractors, specialty trades, suppliers, and owners, and handles the disputes when prevention arrives too late. We work with businesses throughout Marion, Hamilton, Boone, Hendricks, and surrounding counties. Call our Indiana construction lawyers at 317-829-6797 or reach us through our contact form.

The information provided in this article is for general informational purposes only and does not constitute legal advice. Reading this article does not create an attorney-client relationship. For legal advice tailored to your situation, please contact our firm directly by calling 317-829-6797 or by filling out our contact form.